Installation of tripod turnstile
Installation of tripod turnstile:
1. Connect the power, power input: AC220V, 50Hz.
2. Connect the TCP/IP cable.
3. Civil work and fixed work.
Installation of tripod turnstile diagram:
Civil work, using GB 405 # Portland cement concrete, foundation 10CM -15CM thick, 5-7 days after concrete installation.
Fixed work, open the base plate by key, which has 4 12MM hole, fix with 4 8MM * 10MM explosion screws.
Access Control China Co., Ltd. specializes in pedestrian and crowd access control products including door access, door access system, security turnstile, turnstile gate, full height turnstile, tripod turnstile, optical turnstile, turnstile system, retracctable barrier, flap barrier, car barrier, parking barrier, barrier gate, security barrier, barrier system, hotel lock, hotel lock system, fingerprint access, rfid access and rfid access system that are engineered to meet all your security needs.
1. Connect the power, power input: AC220V, 50Hz.
2. Connect the TCP/IP cable.
Fixed work, open the base plate by key, which has 4 12MM hole, fix with 4 8MM * 10MM explosion screws.
Access Control China Co., Ltd. specializes in pedestrian and crowd access control products including door access, door access system, security turnstile, turnstile gate, full height turnstile, tripod turnstile, optical turnstile, turnstile system, retracctable barrier, flap barrier, car barrier, parking barrier, barrier gate, security barrier, barrier system, hotel lock, hotel lock system, fingerprint access, rfid access and rfid access system that are engineered to meet all your security needs.
Related Infomation